For a  Quick Preview Please Click Here

Why Choose us ?

Entire PMP Exam material covered from an ITTO perspective
✔ Covers PMP Basics and all 47 Processes under all 10 Knowledge Areas and all 5 Process Groups
✔ All info at the mouse tips for each and every ITTO, just move the cursor over
✔ Tests your knowledge and understanding of PMP material with 5 timed tests
✔ Very inexpensive, at a throw-away price of $25:00, for the entire material and the tests
✔ Refresh your knowledge and understanding and test yourself
✔ Express your creative mind, submit a CREATIVE question and enter a chance to win a Gift Certificate.

Question of the Day

Referring to the following network diagram, what is the duration of the critical path? What is the float of activity C?

Option A  : 8 days and 20 days, respectively.  
Option B  : 20 days and 8 days, respectively. 
Option C  : 12 days and 8 days, respectively.  
Option D  : 8 days and 12 days, respectively.
 
Please visit our Facebook Page for more sample questions.